From a site to a brief in seven steps

Everything the app asks, in the order it makes sense on site.

An envelope beside a phone
1

Choose the kind of work

Nine kinds, from a new installation or tenant build-out to code corrections. The kind decides which sections the brief needs.

2

Describe the site

Address, size, occupancy, when the work can happen, target months and access notes, plus who Coastline should reply to.

3

Add the existing service

Voltage and phases, rating, and the highest demand measured over 12 months or a 30-day recording.

4

Type the panel directories

Circuit by circuit, as the card reads today. The check lists what to describe better.

5

List the new loads

Each piece of equipment in kVA, kW or amperes at its voltage, marked continuous when it runs 3 hours or more.

6

Count the lighting

Fixtures, watts, hours and days in each area, and the watts of the fixtures that would replace them.

7

Send the brief

Mark the documents you have, read the brief and email it to Coastline from your own email app.

The example, worked out

The made-up example: a 2400 sq ft retail suite fit-out in Fall River, MA
FigureValue
New load, connected31.2 kVA
Planning load, continuous at 125%35.1 kVA (97.5 A on 208Y/120 V 3φ)
Capacity check, 400 A service63.4 A to spare
Panel A directory4 items to fix
Sales floor lighting, a year12,370 → 6,290 kWh

The example and its people are made up. The figures are planning figures, not a code load calculation.